How to use this resource
How
First make a list of all the risks, opportunities, and issues you face and then score them as follows:
- Probability
- Allocate each item on the list a relative probability score: an assessment of how likely each change is compared to other changes on the list. For example, you might assess the probability of a 0.5% increase in interest rates in the next 12 months at 2 out of 5, whereas the probability of a competing product arriving in the market at 1 out of 5. Issues always have a probability of 5 out of 5 as their likelihood isn’t in question.
- Impact
- Similarly, each item needs to be scored for relative impact, positive or negative. Staying with our example, we might find that the increased interest rates would have a slight negative impact, scored at -1 out of 5, given a low exposure to borrowing. However, your product has a poor reputation in the marketplace and so you suspect buyers would flood elsewhere if given the chance. As a consequence, you might score the competing product risk as a -4 out of 5.
- Scoring
- Items are scored by multiplying the probability and impact scores together. In our example, the interest rate increase could be given a score of -2 (2 x -1) and the competing product -4 (1 x -4). Sorting your list by score helps you focus your attention where it’s most needed.
Managing negative impact
When you have a negative score, use the four Ts to try and manage, and potentially reduce, the negative score:
- Terminate
- Eliminate the risk entirely by stopping the activity that causes it.
- Tolerate
- Accept the risk if it’s within your risk appetite and the cost of dealing with it outweighs the benefit.
- Treat
- Reduce the risk by taking action to lessen the likelihood or impact.
- Transfer
- Shift the risk to a third party, such as insurance or outsourcing.
Managing positive impact
In the case of opportunities, aim to increase the potential benefit by using the four opportunity responses:
- Exploit
- Take full advantage by fully committing to the opportunity.
- Enhance
- Do what you can to increase probability, impact, or both.
- Share
- Involve a third party better placed to help you capture the benefit, such as a partner or joint venture.
- Accept
- Take no extra action, but stay ready to benefit if the opportunity arises.
Review your risk register regularly so it remains a living tool rather than a one-off exercise. Managing risks well keeps surprises low, pace high, and plans on track. Below you’ll find an example of a completed risk register.
Example risk register
| Item | Type | Description | Prob (1-5) | Imp (-5 to +5) | Score | Response / next steps |
|---|
| 1 | Risk | Regulatory change affecting product approval | 4 | -4 | -16 | Treat: monitor updates and prepare compliance plan; Transfer: seek specialist legal guidance |
| 2 | Issue | Team member leaving next month | 5 | -3 | -15 | Treat: begin recruitment and redistribute workload |
| 3 | Risk | Delay in supplier delivery | 3 | -4 | -12 | Transfer: review contract terms; Treat: increase communication and build buffer stock |
| 4 | Opp | New client interested in pilot project | 3 | +4 | +12 | Exploit: prepare quick proposal and meet the client to commit |
| 5 | Opp | AI tool could automate a workflow | 2 | +3 | +6 | Enhance: run a test and assess gains to increase the chance of adoption |
| 6 | Risk | IT system outage during peak period | 2 | -5 | -10 | Transfer: ensure strong support contract; Treat: strengthen contingency plan |